VitraHaus, Germany

プロジェクト情報

ロケーション: Weil am Rhein, ドイツ

  • exhibition building on the Vitra Campus
  • 12 reinforced concrete structures with solid gable roofs which create the impression that they have been playfully piled on each other to form a 20 m high group of buildings.
  • shell construction period: 10 month
  • architect: Herzog & de Meuron, Basel

現場でのニーズ

  • different shapes, partly compressed and bent
  • complicated offcuts
  • 15-m components freely protruding
  • short construction time

顧客名

Implenia Bau GmbH, Rümmingen

お客様にとっての価値

  • high construction quality in a very short construction time
Waldemar Scherer, Construction manager, VitraHaus
Waldemar Scherer
Construction manager

I am extremely satisfied with the applied systems and the technical support. We are able to excellently handle the construction project thanks to the technical possibilities of the formwork and scaffolding systems as well as the good cooperation with PERI. Also the high demands of the inspecting structural engineer have always been met. And on top of this, despite the very extraordinary architecture, we are very well on schedule.

提案内容

  • formwork and scaffolding solution for complex shapes and load-transfer
  • formwork unit structure from rentable system parts