You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

Čortanovci Viaduct, Novi Sad, Serbia

プロジェクト情報

ロケーション: Novi Sad, セルビア

  • Support for the construction of the 2.90 km long Čortanovci Viaduct within the Budapest-Belgrade-Skopje-Athens international railway link
  • The viaduct is located on the section between Stara Pazova and Novi Sad as part of the double-track, open railway line and is supported by 59 columns
  • The bridge is divided into a total of five sections A to E, whereby PERI was significantly involved in the construction of sections B and C

現場でのニーズ

  • Realisation of the project within the tight construction schedule
  • High load transfer with support heights of up to 24.00 m
  • Use of a crane
  • Efficient work with high level of safety for site personnel

顧客名

Main Contractor 

RZD International

Subcontractor

Karin Komerc MD

お客様にとっての価値

  • Substantial simplification of assembly work due to the possibility of combining PERI systems on the basis of the modular principle in the common, metric basic grid
  • Project-specific adaptation to geometries and loads in 25 cm steps
  • Force-fit connections and flexible connection points when combining scaffolding and formwork solutions
  • Time-saving relocation of the permanently mounted climbing units by crane lift
  • Fast work due to simplified planning and assembly of the standardised, coordinated components
  • Realisation of the project within the tight construction schedule
  • Increased safety for construction site personnel
  • Individual planning, consulting and support on site by PERI engineers

提案内容

  • Flexible combination of PERI UP as well as components from the VARIOKIT Engineering Construction Kit for realising the 18.50 m high delta piers
  • Erection of the columns using CB Climbing Units as working platforms in combination with the TRIO and VARIO GT 24 Wall Formwork Systems
  • Use of MULTIFLEX Girder Slab Formwork for concreting the two-lane superstructure
  • Support of the MULTIFLEX by PERI UP with a support height of 20.00 m in section C
  • Installation of ALPHAKIT Towers and Lattice Girders for load transfer as well as the creation of horizontal working platforms in section B
  • Assembly of the lightweight ALPHAKIT system components on the ground and by hand: crane use only required for positioning
  • Use of PROKIT EP 110 Guardrail to protect against open building edges
  • Advance planning and support for system implementations