Soon to take its place as the tallest hotel in Seattle, the 46-story 8th & Howell Hotel will offer more than 1,200 luxury rooms in close proximity to the Washington State Convention Center
More than 70,000 square feet of formwork was used to form elevated decks
現場でのニーズ
Construction of the three thick-walled cells that make up the 36-ft by 90-ft core
顧客名
Contractor
Sellen Construction, Seattle, WA
Field Service
PERI Woodland
お客様にとっての価値
The PERI-designed roof structure, made of VARIOKIT components integrated into the climbing formwork, allowed an early start on elevator installation
Large concrete placing booms independent from core size
Significant reduction in construction time and savings in material and installation costs
提案内容
Three PERI ACS Core 400 Automatic Climbing Systems with PERI’s MAXIMO formwork to place the thick walls of the core
PERI MAXIMO Formwork was also used on the perimeter walls with SB Brace Frames on the podium levels and the PERI RCS-P Rail Climbing System on the tower